Vendor Lead Times: The Setup Field That Quietly Drives Every Suggestion
Why does the worksheet always order too late? The usual suspects, reorder points, safety stock, the planning run itself, are rarely the culprit. The culprit is a date field most people set once and never revisit: the Lead Time Calculation on the item card. Business Central's planning does not know when a vendor will actually deliver. It works backwards from the date stock is needed and subtracts the lead times it has been told. If the vendor's real lead time has drifted from the value on the card, every suggested order date drifts with it, quietly, consistently, and in the wrong direction. This myth-check takes the field apart: what the formula subtracts, why transfers play by different rules, and how to audit the values before they cost another late order.
The myth: planning calculates delivery, it only subtracts what you told it
The myth is that the planning engine calculates delivery from live vendor behaviour. It does not. Planning asks when supply must exist for the demand date, then subtracts lead times, safety lead time, manufacturing and transfer times, calendars and dampener rules to find when to order. Every input to that subtraction is setup data a person typed in. The engine's arithmetic is exact; its inputs are only as current as the last person who maintained them. A vendor who quoted three weeks at setup and now takes five has not broken the planning engine, the engine is faithfully subtracting a number that stopped being true.
That is why lead time deserves isolation from the other planning parameters. Reorder points and safety stock decide how much and how much cushion. Lead time decides when, and a when error cannot be fixed by ordering more.
Anatomy of an order date: every component the formula subtracts
For purchase planning from the requisition worksheet, the parameters sit on the item card. The Replenishment tab holds the replenishment system, the Lead Time Calculation, the vendor number and the vendor item number; the Planning tab holds the reordering policy, under Fixed Reorder Quantity, the reorder point, reorder quantity and safety stock. The order date itself comes from one subtraction, stated plainly in the planning walkthrough:
Order Date = Due Date − Vendor Lead Time − Safety Lead Time − Inbound Warehouse Handling Time.
Read it as a chain of promises. The due date is when stock must exist. Vendor lead time is the span the setup claims the vendor needs, on the item card's Replenishment tab for a purchase item, the setup example sets a lead time calculation of 21 days alongside the vendor the item is bought from. Safety lead time is a deliberate extra cushion subtracted on top, so the order goes out earlier than the vendor's own span requires. Inbound warehouse handling time accounts for the gap between the truck arriving and the stock being available to promise. If any one of the three subtracted spans is understated, the order date lands late by exactly that understatement, and because the same field feeds every suggestion for that item, it lands late every time, on every worksheet, until someone corrects the card.
Transfers are different: the three-part lead time and the missing safety leg
Store replenishment often moves stock between locations rather than buying it, and transfer lead time is not the purchase formula with a different label. Transfer order due dates use three lead times: outbound warehouse handling time, shipping time, and inbound warehouse handling time. The dates chain in sequence: shipment date plus outbound handling gives the starting date; plus shipping time gives the ending date; plus inbound handling gives the receipt date.
The difference that catches people out is the missing leg: Safety Lead Time is not included in transfer order calculations. It is not ignored entirely, it influences the replenishment order at the beginning of the transfer chain, the purchase that originally brings the stock in. So a planner who raises safety lead time expecting store transfers to leave earlier will see no change in the transfer dates at all; the cushion lands on the buying leg, upstream, where it may or may not have been the problem. Diagnose a late transfer with the three transfer components. Diagnose a late purchase with the purchase formula. Mixing the two produces fixes applied to the wrong leg.
Find the stale fields: an audit pass over items, SKUs, and vendor changes
- List what planning is actually using. For each purchase item, read the Lead Time Calculation on the item card's Replenishment tab, next to the vendor number it applies to. That pairing matters: the lead time belongs to the item-and-vendor combination the card describes.
- Compare against the vendor's current quoted span. Any item whose card value is shorter than the vendor now quotes is ordering late by the difference, on every suggestion. Correct the card, do not compensate by inflating safety stock, which hides the error in inventory instead of fixing it in the date.
- Check for per-location variation before flattening it. Where an item is planned through stockkeeping units for individual locations or variants, audit the lead time values carried there too; a corrected item card does not fix a stale SKU-level value carried for that location.
- Re-run the worksheet and compare order dates. The corrected items should suggest order dates earlier by roughly the lead time increase, with quantities driven by the reordering policy as before.
What success looks like: for every audited item, the card's lead time matches the vendor's current quoted span, the next worksheet's order dates move earlier by the size of each correction, and nobody can point to a suggestion that is late "for no reason", the reason was a field, and the field is now right.
Governance: who updates lead times when a vendor slips, and how often
- Vendor notifies a longer lead time? The card changes the same week. A known-stale lead time is a decision to order late, taken by whoever filed the notice without updating the field.
- Deliveries drifting without a formal notice? Treat repeated late receipts against suggested dates as the audit trigger: pull the item's card value and compare it with the span the vendor is actually achieving before touching reorder points or safety stock.
- Transfer arrivals late but purchases on time? Work the transfer components, outbound handling, shipping time, inbound handling, and remember safety lead time will not move a transfer date.
- One location consistently later than others on the same item? Check the stockkeeping unit for that location before changing the item card for everyone.
The field is quiet, but it is not minor. Every replenishment suggestion the business acts on is dated by subtracting it, which makes keeping it current the cheapest planning maintenance there is.