Bandwidth and replication windows: scheduling heavy tables for overnight

Data, integrations & replication · 6 min read · By Dex Carter · Published 2026-10-26 · Last updated 2026-10-26

Left, a sunny street with a bicycle carrying a small parcel; right, a moonlit dock where a forklift loads a large crate
Small loads by day, the heavy crate after dark.

Split the estate’s replication into two fleets and schedule them differently. Light jobs, replication by actions, or Normal replication with counters, run through the day in small packages. Heavy Normal-mode tables wait for an overnight window that starts after closing, with each stage chained to finish before the next begins. LS Retail’s warning is the reason: setting all jobs to run with Normal replication causes large data transfers, wasting bandwidth and processing time, and running jobs too often leads to system delays and database locking.

Light fleet, first: jobs that should run all day

The documented recommendation is Normal replication with counters, or replication by actions. Both move changes rather than whole tables. Actions jobs carry a package-size lever of their own: turning off Move Actions when further replication is not required reduces package sizes and improves speed. A daytime fleet built on those modes keeps transfers small enough to share the link with trading.

Small is not free. The same guidance warns that running jobs too often leads to system delays and database locking, so daytime frequency is a setting to justify per job, not a default to copy across the estate. A light job on a tight loop can still tax the database it reads from.

Heavy fleet, second: jobs that should not run at noon

Normal replication should mainly be used for initial data sync or specific tables. That sentence is the classification rule. A table that needs a full Normal pass belongs in the overnight fleet unless a specific, named reason puts it elsewhere, “it has always run at midday” is not a reason, it is how bandwidth problems become tradition.

Light fleet (daytime)Heavy fleet (overnight)
Documented modesReplication by actions; Normal with countersNormal replication, mainly for initial sync or specific tables
Transfer shapeChanges in small packages; Move Actions off where no further replication is required, to reduce package sizeLarge data transfers, the load the bandwidth warning is about
Main riskRunning too often: system delays and database lockingColliding with trading hours: bandwidth and processing time taken from the stores
Scheduling ruleFrequency justified per jobStarts after closing; stages chained so each finishes before the next starts

Classify tables by weight: mode, volume, change rate

No retrieved LS source publishes a ready-made heavy-versus-light table list. The classification has to be built locally, from three questions per table:

  1. Which mode does the table use? Actions or Normal-with-counters tables are light candidates. A table on plain Normal mode is a heavy candidate by default.
  2. How much does a run move? Use the estate’s own job history. A table whose runs are consistently among the largest transfers goes overnight whatever its mode.
  3. How stale can the destination afford to be? Data the stores need during trading justifies a daytime place; data consulted the next morning does not.

Record the answers per table. The classification is a design record the retailer owns, and it is what makes the next section an exercise in sequencing rather than opinion.

Design the overnight window: sequence, buffers, chaining

The one concrete staged schedule in the retrieved LS sources is the Analytics pattern, and its shape transfers even though its payload differs. Recommended timings: start replication after closing hours, at 11 p.m.; run Azure Data Factory pipelines at 1 a.m.; refresh the Power BI dataset at 3 a.m. roughly two hours between stages.

The buffer is softer than it looks. Jobs wait until the earlier job has finished before running, so stage times can be set closer together: the chain enforces order even when a stage overruns its slot. Design the window as a chain, not a set of independent alarms. Heavy replication first, downstream consumers after it, each stage’s start time acting as an earliest-start rather than a promise.

Spec check on that pattern:

ElementDocumented value
First stage startAfter closing hours, 11 p.m. in the recommended pattern
Stage spacingRoughly 2 hours (11 p.m., 1 a.m., 3 a.m.)
Overrun behaviourJobs wait for the earlier job to finish before running
Package-size lever for actions jobsMove Actions off, when further replication is not required

Stagger stores so the window is wide, not tall

Chaining sequences stages at head office. Staggering sequences destinations, and it is design guidance rather than a vendor-documented pattern, apply it as such. Give store groups different earliest-start times inside the window, so the estate’s heavy transfers spread across the night instead of stacking into a single tall peak at 11 p.m.

Two rules keep staggering honest. First, a group’s slot must still leave room for the chain rule: if an earlier group’s jobs overrun, later groups wait rather than collide. Second, stagger by need, not alphabet: groups whose data feeds the earliest morning processes take the earliest slots, and the classification record from the earlier section is where that need is written down.

Change a live schedule without breaking the NAS

Window changes have a mechanical trap. After NAS has started, job schedules cannot be changed from the job card. The documented way through it:

  1. Open Scheduler Setup and deactivate Enable NAS Scheduler. Schedule changes may require this deactivation before the locked schedules can be edited.
  2. Make the schedule changes. Move the heavy jobs into the window, set the chained stage times, and record the change against the classification record.
  3. Restart the service. The documented pattern pairs the Scheduler Setup change with a service restart.
  4. Watch the first night end to end. Confirm each stage started only after the earlier stage finished, and that no daytime light job inherited an overnight slot by accident.

What success looks like: the new schedules hold after the restart, the first overnight chain runs in order, and daytime transfers stay in the light modes. A schedule that only exists until the service restarts is not a schedule change; it is a rumour.

Measure the window: job durations that tell you it is shrinking

A window is healthy while every stage finishes inside it with room to spare. Track three readings per stage: start time, finish time, and the gap before the next stage begins. The chain hides overruns by design, a waiting job is normal, so the shrinking signal is not lateness at the next stage. It is the first stage’s finish time creeping toward the end of the night.

When a stage starts finishing close to morning, act on the classification, not on hope: move a table between fleets, turn off Move Actions where an actions job no longer needs it, or split a store group into two staggered slots. The window is a budget. Spend it on the tables that earned their place in it.

, Dex Carter, Tech Writer