Cutover Weekend Runbook: The 48 Hours Between Old System and LS Central
What has to be true before Monday's first sale? That question, not the software, is what a cutover weekend answers. The generic ERP cutover sequence is well documented, freeze, extract, reconcile, validate, decide, but it says nothing about tills, tenders, or store statements. This runbook takes the documented 48-hour sequence and adds the retail layer: every terminal proved able to trade before the go decision is made, and Sunday kept as a buffer rather than a second Saturday.
A note on sources: the timings and gates below follow published ERP migration guidance. The till-by-till validation layer is this runbook's retail adaptation of that sequence, no generic guide supplies it.
What has to be true before Friday 6pm?
The weekend is won or lost before it starts. Three preconditions from the migration guidance:
- The freeze is communicated to every department at least two weeks in advance. A freeze one department hears about on Friday is not a freeze.
- The go/no-go criteria are agreed weeks earlier, not drafted on Saturday with the data half-loaded.
- At least one mock migration (dry run) has produced control totals: the reconciliation on Saturday is measured against the dry run's totals, and reconciliation is not optional even after three clean dry runs.
Add the retail precondition: the list of terminals, stores, and tenders to be validated on Saturday is written down in advance, till by till. Validation improvised on the day skips the quiet terminal in the corner, which is the one that fails on Monday.
Friday evening: freeze, extract, load
The documented sequence opens the weekend:
- Friday 6:00 PM: the legacy system goes read-only. Lock the legacy systems during the transfer so no late transaction lands in a system that has already been extracted.
- Friday evening into Saturday morning: take the final extract from the legacy system and load it into LS Central. The target sequence in the guidance is to load into a test environment first, prove the load there, then commit to the production path.
- Keep the source extracts. They are the evidence every later question gets answered from; a deleted extract turns a reconciliation query into an argument.
- Log the extract's control totals, record counts and value totals for the data that matters, before anyone touches the loaded data.
Retail note for Friday night: stores that trade Friday evening need the freeze time translated into store instructions, when the last sale goes through the old system, and what happens to anything sold after it. The 6:00 PM freeze is a system event; the stores experience it as a trading instruction.
Saturday morning: reconcile against control totals
Saturday morning belongs to one rule, stated plainly in the migration guidance: no go-live without a signed reconciliation.
- Reconcile the loaded data against the control totals captured from the dry runs and the final extract.
- Reconcile the trial balance to the sub-ledgers line by line, not at summary level, where differences hide inside netting.
- Add the retail control totals the generic guides omit: stock value by store, open orders carried over, and the tender picture the stores will open with on Monday. Each total is compared old system against LS Central, and each difference is explained or fixed, never carried as "close enough."
- The reconciliation is signed by its owner when it passes. The signature is what the afternoon's go/no-go decision stands on.
What success looks like: every named total agrees or has a written, accepted explanation, and the signed reconciliation exists as a document, not as a verbal "looked fine" in a corridor.
Saturday afternoon: prove the tills can trade
Functional validation is the documented Saturday step. For a retail cutover, validation has a specific meaning: a till that cannot complete a sale is a failed validation, whatever the back office shows. Work the pre-written terminal list, every terminal, in order:
- Open the POS on the terminal and confirm it starts against the store it belongs to.
- Run a test sale for each tender type the store accepts, and confirm each tender behaves as configured.
- Print a receipt and confirm the printer path works from that terminal.
- Run the terminal's statement or end-of-day routine on the test activity and confirm it produces a clean result.
- Confirm the terminal's activity is visible centrally, the sale made in the store is data head office can see.
- Mark the terminal passed or failed on the list. A failed terminal is fixed and retested, or it is explicitly excluded from Monday trading, never left as "probably fine."
What success looks like: a completed list with a pass against every terminal that will open on Monday, and a named decision for every terminal that did not pass.
The go/no-go: criteria, owners, and the rollback line
The documented decision point is Saturday 6:00 PM, judged against the criteria agreed weeks earlier. For a retail cutover, the criteria table looks like this:
| Criterion | Owner | Pass condition |
|---|---|---|
| Signed reconciliation | Finance owner | Trial balance reconciled to sub-ledgers line by line; retail control totals agreed |
| Till validation | Store systems owner | Every Monday terminal passed the trade test, or is excluded by name |
| Rollback readiness | Cutover lead | Rollback procedure prepared, with trigger criteria and a communication protocol |
| Support coverage | Cutover lead | Trained support rostered, 24/7 coverage for the first 72 hours, extended hours for the rest of the first week |
Rollback is part of the decision, not a defeat drafted afterwards: prepare the rollback procedures in advance, with the trigger criteria, the specific conditions under which the weekend reverses to the legacy system, and the communication protocol for telling stores what is happening. Decide the triggers on Saturday while the option is still cheap; on Monday morning it is not an option, it is a crisis.
A no-go is a legitimate outcome of this meeting. It means the criteria did their job before customers were involved.
Sunday: buffer, access, printers, and Monday's first sale
Sunday's role in the documented sequence is one word: buffer. Protect it. Sunday is for:
- Absorbing the overrun of a Saturday step that ran long, the one legitimate use of the buffer.
- Final physical checks in stores: printers loaded, terminals in place, staff able to log in.
- Confirming the support rota for the first 72 hours is staffed and reachable.
- Resting the team that will support Monday. A team that spent Sunday firefighting starts the hardest day of the project already spent.
What Sunday is not for: starting the migration, re-running the reconciliation from scratch, or discovering a new requirement. Anything that surfaces on Sunday and cannot be fixed inside the buffer goes through the rollback triggers or the no-go path, it does not quietly eat Monday.
The 48-hour runbook on one page
| When | Step | Done when |
|---|---|---|
| Before Friday | Freeze communicated (2+ weeks ahead); go/no-go criteria agreed; dry-run control totals captured | All three exist in writing |
| Fri 6:00 PM | Legacy goes read-only and is locked | No writes possible |
| Fri night, Sat morning | Final extract, load (test environment first), source extracts kept | Load complete, extracts archived |
| Sat morning | Reconciliation against control totals, trial balance to sub-ledgers line by line | Reconciliation signed |
| Sat afternoon | Till-by-till validation: sale, tenders, receipt, statement, central visibility | Every Monday terminal passed or excluded |
| Sat 6:00 PM | Go/no-go against the pre-agreed criteria | Decision recorded, rollback triggers known |
| Sunday | Buffer, physical checks, support rota confirmed | Stores ready, team rested |
| Mon to Wed | Hypercare: 24/7 support for the first 72 hours, extended hours after | First week traded |
Forty-eight hours is enough for a retail cutover, provided the weekend is spent proving the new system, not still building it.